Look what’s in straw
The UK’s first straw bale council houses are nearing completion. Caroline Thorpe checks out their environmental credentials
What A pair of three-bedroom, semi-detached straw bale homes for affordable rent, with two more in the pipeline
Where Waddington and Martin, Lincolnshire
Who North Kesteven Council, Taylor Pearson and Amazonails
How much £110,000 per home
How long Seven months
Code for sustainable homes Level 4
SAP rating Likely to exceed 7
Environmental impact 89
Funding £75,000 is the most commonly quoted cost of building a straw bale home. It’s way off the mark, advises Michael Gadd, property manager at the council, who says the figure applies to self-build properties. North Kesteven has budgeted £110,000 per property, which includes the contractor’s fee and sustainable materials. ‘We could have done it a lot cheaper and a lot quicker using much less expensive materials,’ adds Mr Gadd.
The property manager hopes the second pair of semis in the nearby village of Martin, will come in under budget, ‘because we’ve learnt
all the lessons’.
All four of North Kesteven’s straw homes are funded equally by the council and the Homes and Communities Agency, which has awarded the authority £3.7 million to build 35 new homes for rent, including the straw dwellings.
It’s a question to pose: why do people want to build with straw?’ It’s a strange question, coming as it does from the man who will soon be able to add ‘building the UK’s first straw bale council houses’ to his CV, before embarking on building some more. But then Michael Gadd, property manager at North Kesteven Council, has found his own answer to that question change several times throughout the groundbreaking project.
The pair of straw semis in the Lincolnshire village of Waddington, which will hit level four of the code for sustainable homes when completed in March, were conceived two years ago as an exemplar project to encourage local people to build their own energy efficient homes. When funding difficulties put paid to the self-build promotion plan, the only way to get the homes started was to build them for social rent using some of the council’s £3.7 million in Homes and Communities Agency development grant.
Now the project had a different aim. ‘The emphasis changed in our minds,’ explains Mr Gadd. Instead of using the homes as a training programme for potential self-builders, it became ‘to get contractors and designers to accept it as a method of construction’. Straw construction, a US import, arrived in the UK as recently as 1994. Since then it has mainly been used by self-builders. Mr Gadd knows of just two contractor-built straw buildings: a commercial development in Essex and a community hall in Yorkshire.
‘Find a contractor who’s willing to learn… [or] you will have a fight every step of the way,’ advises Mr Gadd. North Kesteven picked local contractors and straw-bale virgins Taylor Pearson, whose staff received onsite training from straw construction experts from not-for-profit designers Amazonail.
Sourcing certain materials, such as the lime rendering and sheep’s wool insulation, was tricky. ‘At the moment they are not standard, off-the-shelf materials. The argument is that if everyone started using them they would become more readily available. General builders merchants don’t stock them,’ says Mr Gadd.
Using more traditional materials to insulate the home would have been both cheaper and, ultimately, made no difference to the properties’ energy efficiency - a projected SAP rating of at least 74. Which is when the real questions started.
‘You’ve got to think about what you’re actually trying to achieve,’ cautions Mr Gadd.
‘Are you trying to build energy efficient houses or eco-friendly and green houses, because there’s a difference between the two, and we’ve switched between the two.’
It’s a question more and more landlords could find themselves facing. Mr Gadd says other providers have visited the scheme seeking inspiration, with more scheduled. ‘Part of the idea was to prove it could be done so others can follow,’ he says. Job done.
Timeline
August 2009
Straw bales arrive on site in Waddington. Building with straw commences, and designer Amazonails’ training courses begin
September
Pre-constructed, traditional roofs are crane lifted, ready for placement. Roofs lowered on to completed straw bale walls
October
Staircases installed; first and second stages of lime rendering completed. Tiling and solar panel installation completes roofs
November
External lime rendering completed; internal rendering begins
December
Scaffold removed and buildings weather-proofed. Contractors press on with internal fittings and plastering
January 2010
First internal fixings carried out. External walls complete
March
Waddington site due to complete, then on to the site at Martin
Foundations
Compacted gravel trench with 450mm limecrete capping.
Plinth wall
Engineering brickwork and Foamglas T4 blockwork to inner skin (recycled glass blocks). Cavity filled with LECA (lightweight expanded clay aggregate).
External walls
Loadbearing straw bale pinned together with hazel pins with 30mm lime render to external and internal face. ‘Ideally you need to get the external lime rendering on by the end of September. It’s dictated by the weather, and you need it to dry,’ explains Mr Gadd.
Ground floor and first floor
FJI joists with 300mm sheepswool insulation to ground floor. Both floors clad in Smartply (T&G plywood made with no glues or formaldehydes).
Roof
Traditional truss roof with old English pan-tile, 300mm insulation to roof space. Solar thermal panels to south elevation roof. Sedum roof to main entrance porch.
External windows and doors
Low E timber double glazed doors with an argon filled cavity. Low E timber triple glazed windows with argon filled cavities.
Sanitary fittings
Low-flow taps, a smaller-shaped bath and low flush WCs installed to reduce water consumption.



Have your say
You must sign in to make a comment