Is the money in the bag?

At what point does HCA grant approval become legally binding? Naomi Goode explains

Sir Bob Kerslake, chief executive of the Homes and Communities Agency, has said that the HCA will not be able to guarantee funding-approved schemes unless there is already a legal commitment in place (Inside Housing, 11 June).

So when does a grant approval become legally binding? The brief answer, as expanded on below, is that the HCA becomes legally committed to provide grant funding at the point at which it signs off the grant agreement online (ie on its Investment Management System).

The contract

Once grant funding has been approved, the HCA and the social landlord will enter into a legally binding contract which is known as the Programme Partnering Agreement.The PPA sets out the HCA’s and the social housing provider’s rights and obligations. Each PPA will include an annex listing the schemes to be developed, and stating the amount of the grant and the relevant forecast milestones. The programme of schemes, as detailed in the annex will be input into the HCA’s IMS.

Social housing providers must confirm within IMS that they agree to the terms of the PPA. Accordingly, the social housing provider will sign off online to accept the agreement. The HCA lead investor will then approve/accept the submission online. While the PPA itself is a legally binding agreement, it is the acceptance by the HCA of the online submission in IMS that forms the binding contract and the HCA’s commitment to fund.

Can grant be withheld?

The standard PPA model provides that ‘the corporation [as was] will make grant payments upon receipt of valid claims, in line with agreed liability dates’. It goes on to say that ‘where a scheme achieves start on site or practical completion in advance of its forecast milestone date (which has been accepted as the liability date as set out in IMS), the corporation is not obliged to make grant payments until that date. The corporation is not obliged to recognise the liability to make payment until the contractors start on site or completion date is reached.’

There are circumstances under which the HCA may lawfully withhold or reduce grant, for example, if the social housing provider fails to meet high Tenant Services Authority regulatory standards, if it breaches the grant conditions, or if the HCA is required by the European Commission under state aid rules to obtain repayment of the grant from the social housing provider. But in the absence of these circumstances, the HCA is legally obliged to make the payments on the milestone dates.

In the past, social housing providers have tended to treat written confirmation from the HCA that they have an allocation as sufficient to go ahead and enter into building contracts, without waiting for online grant confirmation on IMS. But in the the current economic climate, this may no longer be common, or indeed prudent, practice.

Naomi Goode is a partner at Lewis Silkin naomi.goode@lewissilkin.com

Have your say

You must sign in to make a comment

sign in register

Related

Articles

  • New horizons

    09/12/2011

    Landlords could benefit from looking to Europe and forming multinational housing associations

  • Leading man

    06/05/2011

    How will the green deal work in practice? Nick Duxbury talks to Michael O’Doherty, the man trailblazing the UK’s first ever pilot scheme, to find out

  • Stick or Twist

    18/03/2011

    Only landlords that agree to shoulder more risk will qualify for state development funding from now on. Will they decide the stakes are worth playing for? Don’t bet your house on it, says Carl Brown

  • Easy on the Planet

    4 October 2011

  • Increased council borrowing could deliver homes

    27 September 2011

    A group of housing experts has called on the government to increase local authority borrowing powers to deliver more affordable homes.

Resources

  • Weather any storms

    02/09/2011

    New guidelines will help landlords comply with the Human Rights Act, says Nnenna Morah, senior associate in the social housing team at Lewis Silkin

  • Unlocking funds to build

    26/08/2011

    Associations must work carefully to secure their development grant, says Gillian Bastow, partner at Lewis Silkin

  • A spanner in the works

    25/03/2011

    Landlords must take care when passing repair costs on to tenants, says Simon Bagg, senior associate in the property litigation team at Lewis Silkin

  • Shout it from the rooftops

    06/01/2012

    Further planning rules under the Localism Act could increase the need to consult residents, says Ben Halsey, senior associate at Lewis Silkin

  • A huge relief

    21/04/2011

    Though the government is not scrapping the community infrastructure levy, social housing will qualify for relief from paying it, says Paula Ghosh, senior associate at Lewis Silkin

Latest Jobs

  • Development Manager

    One Housing Group is a leading provider of housing care and support across London & the South East managing over ...

    £39,200 - £46,200

    Closing: 2012-01-22 00:00:00

  • Head of Design and Procurement

    £50,425 pa

    Closing: 2012-02-21 00:00:00

  • Head of Neighbourhood Investment

    Eden Brown ( www.edenbrown.com ) are exclusively recruiting for a Head of Neighbourhood Investment for our client a Housing Association ...

    £60,094

    Closing: 2012-02-16 00:00:00

  • Growth & Partnerships Development Manager

    Equity Housing is a fast growing Housing Association who have undertaken a strong development plan across the North West region. ...

    Competitive

    Closing: 2012-02-17 00:00:00

  • Sales Officer

    We are seeking a Sales Officer to manage the disposal of Metropolitan Housing Partnership's Intermediate and private sale, re sales ...

    £29274 - £29274 annum