Friday, 25 May 2012

Substructure

From: Passivhaus blog

Through 11 sets of road works along the A9 we finally made it to site to find that the weather had been a little kinder to our team at O’Brien Properties and, with all of our concrete strip founds in place and two thirds of our sub-structure walls complete, we could start to appreciate the scale of our terrace and its relationship to some of the other units on adjacent plots.

Blockwork

Blockwork on plots 11/12

For the sub-structure, we are using an Aerated concrete block to help significantly with our U-Values and thermal bridging.  A common concrete block wall would not have provided us with sufficiently low thermal conductivity or indeed a suitable fixing base for the wide prefabricated timber panels which need to be anchored down to resist the significant wind loads experienced on such an exposed site.

Passivplate

Passivplate delivery for plots 11/12

We did consider importing a unique German foundation system called ‘Isoquick’ which uses modular foam blocks to create a foam ‘tub’ into which the concrete slab can then be poured.  It was ideal for Passive House construction but we couldn’t satisfy ourselves that it could deal with the stepped profile of our terrace or more importantly the significant wind loads it had to withstand.  We have however decided to do some more research into this product for our next Passive House project as it would minimise many of the cold bridging issues we have come across.  In the end we went for the best solution available in the wide format Aerated blocks although I don’t think we’ve been the brickie’s best friends!

Scottish housing expo

Rural Design + James McQueen Builders – Plot 17

Given the stringent standards for thermal performance in Passive House construction we have had to accurately model every junction to understand and predict the heat loss of the buildings accurately.  This was done in conjunction with the Scottish Passive House Centre using the Passive House Planning Package (PHPP) software, a widely accepted energy design tool for Passive Houses which is frequently updated with numerous years of experience from built Passive House projects.  The tool itself is fairly complex but helped us to look at every heat loss and heat gain associated with thermal conductivity, thermal bridging, air-tightness, ventilation, solar gains and internal gains.  PHPP very simply establishes a number of rules and conventions against which we can test our design.  For us it simplifies the design process and the route towards the eventual Passive House certification.  It’s far more advanced and relevant than the current UK norm, the standard assessment procedure (SAP).

Warmcell insulation

Warmcell insulation being blown in on David Blaikie Architects plot

RTC have more or less finalised the manufacture of the timber frame panels with only the roof panels to complete, set for delivery soon.  Whilst we were on site RTC made the first delivery of their patented Passive Wall Plates which act as wall plates for their Passive Wall system and help achieve significant air tightness in the wall panels. We have talked about the lead in times on the window delivery and have decided that the timber frame openings will need to be covered sufficiently to allow some first fix works internally to proceed.  We also think we can get the triple glazed roof lights in, the profiled roof sheeting on and some of the external wall cladding framing commenced before we absolutely need the windows and doors!

The block work is complete this week and the drainage is in place and our insulation and concrete slab is in place awaiting the Passive Wall panels.

Progress varies around the site with most ground works underway and even some timber frames complete.

The snow returned again though and the site looked as though it’s the middle of winter again.  We can’t believe the impact the weather has had on this project this year but everyone’s still confident everything will be ready in time!  I wonder if there’s some snowmen being built just out of picture?!

Snow

The snow’s back

Readers' comments (2)

  • i like the concept, i worry about the apparently low level of fenestation -- per picture -- and about condensation/smells if as airtight as implied

    Unsuitable or offensive? Report this comment

  • Most people do initially! However there is a basic Mechanical Ventilation system which works with Heat recovery and pulls out all the stale air replacing it with fresh air. Analysis shows that the indoor air quality within a passive house is substantially better quality than we might normally expect from a new build house making it ideal for allergy and asthma suffers also. Saying that, theres nothing to stop you opening the windows if you want to - particularly in summer.

    Unsuitable or offensive? Report this comment

Have your say

You must sign in to make a comment

sign in register

From Passivhaus blog

HLM Architects are building some of the first UK homes to meet the German Passivhaus standard for Scotland’s Housing Expo this summer. Here the firm will update on progress.

Ross Barrett writes about

passive house, scotland housing expo