ao link
Twitter
Facebook
Linked In
Twitter
Facebook
Linked In

Grenfell Tower Inquiry diary week seven: ‘I do not think I have ever worked with a contractor operating with this level of nonchalance’

Two key witnesses from contractor Rydon gave evidence this week. Peter Apps recaps some of the key points from a revealing week of evidence

Linked InTwitterFacebookeCard
Sharelines

Two key witnesses from contractor Rydon gave evidence this week. Peter Apps recaps some of the key points from a revealing week of evidence #ukhousing

Grenfell Tower Inquiry diary week seven: “I do not think I have ever worked with a contractor operating with this level of nonchalance” #ukhousing

This week the inquiry heard witnesses from Rydon, the contractor which took on the design and build responsibility for the Grenfell Tower project from April 2014 onwards. Simon Lawrence, contracts manager, and Simon O’Connor, the project manager who ran the onsite operation, gave evidence this week.

Pocket the difference

A big focus of this module of the inquiry has been value engineering: the process of substituting materials for cheaper versions, which, in the case of Grenfell Tower, drove the move to the deadly aluminium composite material (ACM). We learned a good deal about this process this week.

Rydon had bid alongside two other contractors for the work when it went out to tender in autumn 2013. On 11 March 2014 – before the process finished – the firm got an unofficial tip off from Kensington and Chelsea Tenant Management Organisation (KCTMO) that they were “in first place”.

But KCTMO was clear that further cost saving was necessary to bring the project within budget. In an email on 13 March it noted that “our target [for savings] is circa £800k”.


READ MORE

‘We will be quids in,’ Rydon manager says in email about Grenfell cladding switch‘We will be quids in,’ Rydon manager says in email about Grenfell cladding switch
Grenfell contractor Rydon ‘should not bid for public work’ says JenrickGrenfell contractor Rydon ‘should not bid for public work’ says Jenrick
Rydon ‘relied on others’ to check Grenfell cladding compliance, inquiry hearsRydon ‘relied on others’ to check Grenfell cladding compliance, inquiry hears
Rydon manager brands Grenfell residents who complained about fire safety ‘aggressive’Rydon manager brands Grenfell residents who complained about fire safety ‘aggressive’
Rydon planned to ‘pocket’ savings from Grenfell Tower cladding switch, inquiry hearsRydon planned to ‘pocket’ savings from Grenfell Tower cladding switch, inquiry hears

But Rydon itself was in difficulty. Its finance team discovered one member of staff, Frank Smith, had made an error preparing the bid (described in internal emails as a “Frank-ism”) that meant they had budgeted £212,000 too low.

As counsel to the inquiry Richard Millett QC put it: “You are underwater. You have got to find over £1m of value engineering in order both to satisfy your client and to maintain your profit level.”

Rydon then secured a quote from subcontractor Harley Facades as to what saving could be made by switching the cladding to ACM from the more expensive zinc option as originally planned, which quoted either £419,627 or £576,973 depending on the type of fixing used. But when Rydon presented this to KCTMO, it said the savings would be £293,368 or £376,175. Mr Millett asked Mr Lawrence to account for the difference.

“I would suggest by that, although not my area of expertise, that Rydon took some of the saving for themselves,” he replied.

“Did you know that at the time?” asked Mr Millett.

“I think I probably did, yes,” replied Mr Lawrence, noting openly that the money “probably went into, effectively, additional profit”.

“Was the plan in Rydon to keep the TMO in the dark about the real extent of the savings on the ACM panels and then pocket the difference to make up the shortfall caused by Frank Smith’s £212,000 estimating error?” asked Mr Millett. “That could be the reason for it,” said Mr Lawrence.

‘Essex boy patter’

Once the decision had been made to switch out the zinc for ACM to save this money, the next job was to persuade the planning committee at Kensington and Chelsea Council to give permission for this change.

This committee was preoccupied with aesthetics and favoured the zinc above the look of the ACM, which they had snootily described as looking too much like something from (south London borough) “Croyden [sic]”.

In an email on 6 May, ahead of a key meeting with the planners, Mr Lawrence said the purpose was to “propose the material change from zinc to ACM… so KCTMO can maximise their [value engineering] target”. He talked about a plan to “put forward our case that ACM is not an inferior product to zinc”.

Under cross-examination he said that fire safety was not part of this consideration, it was just aesthetics and durability. He described zinc as “a fairly luxurious material”.

However, another email did emphasise that the ACM had a ‘Class 0’ rating – although he said this was just to “give... as much information as I had”. Mr Lawrence admitted he had received a certificate relating to the fire performance of the ACM, but said he had not read it “cover to cover” and relied on the specialists to understand it.

While the planners did accept the switch to ACM, they did not accept a further change – using cheaper face-fixed panels which are essentially riveted into position as opposed to the more expensive ‘cassettes’ which are cut in a way which allows them to be hung from rails and hidden from view.

Mr Lawrence did his best to persuade the planners to accept this change: “I’m giving it my hardest sales pitch as we speak. Come on the Essex boy patter!,” he wrote in an email.

But the aesthetic concerns won out and the planners insisted on hidden fixings. This was a fateful decision: we know now that the cassette panels have a far worse fire performance than the cheaper riveted versions.

Mr Lawrence gives evidence to the inquiry
Mr Lawrence gives evidence to the inquiry

Rebel residents

Another headline topic this week has been the way complaints by residents were dealt with by Rydon and KCTMO.

Mr Lawrence (and later Mr O’Connor) were shown a series of emails referring to complaints and concerns, which made it clear that there was a view among the team that some residents of the tower were essentially difficult and annoying regular complainers.

We saw that a question Rydon was asked in the tender interview is how it would cope if residents “encouraged negative press involvement”.

Mr Lawrence said he had been briefed in advance by KCTMO that “there were several vocal residents, one of which could be extremely vocal and was quite well known by the TMO”.

Pressed, he confirmed this was a reference to Eddie Daffarn, one of the authors of the Grenfell Action Group blog, which tried to raise fire safety concerns before the blaze.

In one email Mr Lawrence noted being “under massive pressure and criticism from the rebel residents about our quality of work”.

In one specific email, Mr Daffarn wrote: “It should be residents that have a say in the type of windows and cladding we receive, not the sole decision of a town hall planning department.”

In another, Mr Lawrence was shown complaints about a damaged self-closer on a fire door in Flat 136 – an issue which had not been fixed by the night of the fire.

A further email from Mr Lawrence and KCTMO noted: “I’ve not mentioned the need to fix through asbestos ceiling for the pipe work boxing if the HIU [heat interface unit] is in the kitchen cupboard. I assume you don’t need to be questioned on this by Mr Daffarn.”

Reference was also made to Rydon workers being “very aggressive and threatening”, no water being provided when water was turned off and lifts being put out of service.

Mr Lawrence made no apology, insisting that “we were always courteous with the residents”.

He then made several references to the residents being aggressive. “I think there were several very vocal, dare I say aggressive residents that, in my opinion, regardless of what work was being carried out or not, they still would have had reason for complaint,” he said.

lacknall moment

The aftermath of the Lakanal House fire (picture: Press Association)

A ‘Lacknall’ moment

Mr Lawrence was also grilled about a crucial moment in November 2014, when KCTMO queried the fire safety of the planned cladding works with him. This was after the plans had been finalised but before the cladding was fitted – so a time when a change could have been made.

Having been struck by a memory of the Lakanal House blaze in south London in 2009 (which killed six after spreading via combustible window panels), Claire Williams, project manager at KCTMO, emailed her consultant Artelia on 12 November to say: “I have just been looking at the cladding as our database is asking for costs...

“However, I do not know if there is any issue of flame retardance requirement? I know at Lacknall [sic] House one issue was that the replacement panelling for the asbestos cladding was not flame retardant! I don’t know if this is in the specification, but want to make sure it is raised. Please advise.”

She was told to email Mr Lawrence and sent him a note that said: ”Simon, I am just writing to get clarification on the fire retardance of the new cladding – I just had a ‘Lacknall’ moment.”

Mr Lawrence did not respond. Under cross-examination he said that she was simply referring to a small amount of glass reinforced cladding on the lowest floors of the tower, because this was the element she included in her email (copy and pasted from the design specification).

Mr Millett reacted to this answer sceptically. After grilling him for some time on this interpretation, he said: “This document, I know, is a well-known document in the disclosure. Did you have any assistance in preparing to give evidence to the inquiry today and in the last few days about what sort of answers you should give in relation to this document?”

“No,” Mr Lawrence answered.

step 2 diary

The panel listen to Mr O'Connor's evidence (picture: Grenfell Tower Inquiry)

‘I did not have the technical expertise and ability to check the designs’

From 2014 onwards, Rydon was the design and build contractor in charge of the Grenfell Tower refurbishment and contractually responsible for ensuring the works complied with building regulations.

This raises difficult questions for the firm about what it was doing to fulfil this obligation, a subject Mr Millett returned to again and again during the week.

Mr Lawrence repeatedly made Rydon’s general position clear: it believed that by appointing subcontractors and securing building control sign off, it had done enough to discharge this duty.

For example, when asked about the missing cavity barriers at the top of the system (a requirement of building regulations), he said: “I would have expected Harley to do it right in the first place, I would expect them to pass it to Studio E for comment, I would then expect it to go to building control... I did not have the technical expertise and ability to check the designs.”

Asked about many key emails or product sheets, he said he had either not read them or only read them in a “high level” or “cursory” way, assuming others in the chain would be checking them.

This led to a key decision from Rydon early in its time on the project – the decision to dump key fire consultant Exova from the team.

Despite telling a meeting in April 2014 that he would “contact [fire engineer Exova] with the view of using them going forward” and repeating this assurance through to October, Mr Lawrence told the architects that he did not feel fire consultants were necessary as building control inspectors would ensure the designs complied with regulations.

This meant that Exova’s fire safety report – which had yet to formally consider the cladding – was never completed.

All of this posed a specific question: how could Rydon comply with its contractual obligations to check the design without the necessary expertise? As well as a general one: how can a design and build contractor do its job without a design team?

As Mr Millett put it: “If you didn’t have a design team in house or an in-house expertise for design, how could Rydon operate a design and build business?”

“Because they relied on third parties to do that,” replied Mr Lawrence. “Which in my experience is standard throughout the industry.”

step 3 diary 7

An image of a poorly fitted cavity barrier (picture: Dr Barbara Lane)

‘I do not think I have ever worked with a contractor operating with this level of nonchalance’

When project manager Mr O’Connor took to the stand on Thursday, he was asked detailed questions about Rydon’s onsite management of the works.

Again, much was left to subcontractors, with Rydon only checking the finished details against drawings after installation – right down to the fact that he was not even checking what materials were coming onto site and being installed to ensure they matched the design.

Mr O’Connor referred repeatedly to being “under pressure” with the project slipping some 12 weeks behind schedule.

Discussing his departure from Rydon in summer 2015, he said: “It was starting to fall behind programme and, you know, when that happens, pressure happens... Extremely long days, you know, just a lot of pressure… it was affecting my home life.”

These difficulties led to frustrations from KCTMO’s consultants Artelia, which wrote in May 2016: “This is becoming a farce. Despite all our efforts to ensure a smooth landing, I have to say I do not think I have ever worked with a contractor operating with this level of nonchalance.”

With regard to the quality of the work, two particular issues were raised. First the fitting cavity barriers for the cladding system – designed to prevent fire ripping through it – which were described as “shockingly poor workmanship” by Mr Millett.

Mr O’Connor was unable to explain how this had slipped through the quality control systems in place.

Second was windows. The refurbishment saw new windows fitted in all flats in the tower. These have been identified as a crucial piece in the disaster, in explaining how the fire broke out of the flat of origin and back in to those higher up the building.

One issue was the decision to pack the gap between the old and new windows with highly combustible insulation instead of non-combustible mineral wool, as specified.

Rydon subcontracted this work to SD Plastering, but not the design elements, meaning it retained responsibility for the design. So why did it not meet the specification?

“We should have checked it,” Mr Lawrence said. “But I would have expected those managing the works on site to have a closer grip on the… specification than someone like myself, but I do agree we should have checked it.”

But when Mr O’Connor was asked if he appreciated that filling the gap with Celotex was a risk, he replied: “I didn’t see it particularly as an issue, as the whole building was being covered in [Celotex] and someone far more intelligent than me had designed it.”

“I don’t think we were cognisant that there were regulations relating to the window linings internally,” Mr Lawrence added. “We thought it was an aesthetic finish product.”

Undoubtedly, this does point to a bigger issue in the industry: there are thousands of tower blocks with combustible insulation around windows.

What’s next?

Next week we will hear from further Rydon witnesses, including those who took over after Mr Lawrence and Mr O’Connor left the project.

Grenfell Tower Inquiry: week seven news stories

Rydon planned to ‘pocket’ savings from Grenfell Tower cladding switch, inquiry hears

Rydon sought to “pocket” more than £100,000 of the savings made by switching to the deadly aluminium composite material cladding on Grenfell Tower by hiding the true costs from its client.

Rydon contract manager used ‘Essex boy patter’ to push cheaper cladding option for Grenfell

Rydon’s contract manager used “Essex boy patter” to push the use of cheaper cladding options for Grenfell Tower.

Rydon manager brands Grenfell residents who complained about fire safety ‘aggressive’

The contracts manager for Rydon during the Grenfell Tower refurbishment described residents who raised complaints about fire safety and cladding as “vocal and aggressive”.

‘Shockingly poor workmanship’ went ‘unchecked’ in Grenfell cladding system, inquiry hears

Rydon’s project manager for the Grenfell Tower refurbishment was unable to explain the presence of “shockingly poor workmanship” on cavity barriers in the cladding system installed on the building.

Grenfell Tower Inquiry phase two: weekly diaries

Grenfell Tower Inquiry phase two: weekly diaries

Module one: the refurbishment

Week one: A vivid picture of a broken industry

After a week of damning revelations at the opening of phase two of the Grenfell Tower Inquiry, Peter Apps recaps the key points

Click here to read the full story

Week two: What is the significance of the immunity application?

Sir Martin Moore-Bick has written to the attorney general requesting protection for those set to give evidence at the Grenfell Tower Inquiry. Peter Apps explains what the move means

Click here to read the full story

Week three: Architects of misfortune

This week saw the lead architects for the Grenfell Tower refurbishment give evidence to the inquiry. Peter Apps runs through the key points

Click here to read the full story

Week four: ‘I didn’t have any perception that it was the monster it’s become’

The architects continued to give evidence this week, outlining a lack of understanding of the fire risk posed by the cladding materials and its design. Nathaniel Barker reports

Click here to read the full story

Week five: ‘No adverse effect in relation to external fire spread’

As the Grenfell Tower Inquiry returns from its long absence, Peter Apps recaps the key points from a week of important evidence from the fire consultants to the refurbishment

Click here to read the full story

Week six: ‘I can’t recall any instance where I discussed the materials with building control’

Nathaniel Barker summarises what we learned from fire engineers Exova, architects Studio E and the early evidence from contractor Rydon

Click here to read the full story

Week seven: ‘I do not think I have ever worked with a contractor operating with this level of nonchalance’

Two key witnesses from contractor Rydon gave evidence this week. Peter Apps recaps some of the key points from a revealing week of evidence

Click here to read the full story

Week eight: ‘It haunts me that it wasn't challenged’

Four witnesses from contractor Rydon gave evidence this week. Lucie Heath recaps what we learned on the last week of evidence before the inquiry breaks for five weeks

Click here to read the full story

Week nine: ‘All I can say is you will be taken out for a very nice meal very soon’

This week the inquiry heard evidence from witnesses at Harley Facades, the sub-contractor responsible for Grenfell Tower’s cladding. Peter Apps recaps the key points

Click here to read the full story

Week 10: ‘As we all know, ACM will be gone rather quickly in a fire!’

As the Grenfell Tower Inquiry entered its 10th week, Jack Simpson recaps the key points from a week of important evidence from the refurbishment’s cladding contractor

Click here to read the full story

Week 11: ‘Did you get the impression Grenfell Tower was a guinea pig for this insulation?’

With witnesses from the cladding subcontractor, the firm which cut the deadly panels to shape and the clerk of works which inspected the job giving evidence this was week full of revelations. Peter Apps recaps the key points

Click here to read the full story

Week 12: ‘Would you accept that was a serious failing on your part?’

With the surveyor who inspected Grenfell Tower for compliance giving evidence, this was a crucial week from the inquiry. Dominic Brady and Peter Apps report

Click here to read the full story

Week 13: ‘Value for money is to be regarded as the key driver for this project’

With consultants to Kensington & Chelsea Tenant Management Organisation (KCTMO) giving evidence, attention at the Grenfell Tower Inquiry turned for this first time to the actions of the TMO and the council. Peter Apps reports

Click here to read the full story

Week 14: ‘Did it not occur to you at this point that your budget was simply too low?’

This week, for the first time in phase two, the inquiry heard from Kensington & Chelsea Tenant Management Organisation, the landlord that oversaw the fatal refurbishment of Grenfell Tower. Lucie Heath reports

Click here to read the full story

Week 15: ‘Have you ever informed the police that you destroyed documents relevant to their investigation?’

Witnesses from the Kensington and Chelsea Tenant Management Organisation (KCTMO) gave evidence for a second week, which began with a shocking revelation about withheld and destroyed evidence. Peter Apps recaps

Click here to read the full story

Week 16: ‘I conclude this was very serious evidence of professional negligence’

This week saw members of Kensington & Chelsea Tenant Management Organisation finish giving evidence, before the inquiry’s expert witnesses took the stand to make some highly critical assessments of the work they had seen before and during the refurbishment of Grenfell Tower. Jack Simpson recaps

Click here to read the full story

Grenfell Tower: a timeline of the refurbishment

Following the conclusion of module one of the Grenfell Inquiry’s second phase, Peter Apps presents a timeline of the key moments during the fatal refurbishment of the west London tower block

Click here to read the full story

Module two: the cladding products

Week 17: ‘It’s hard to make a note about this because we are not clean’

The start of the second module of the Grenfell Tower Inquiry phase two came with some huge revelations about the companies that sold the products used in the cladding system. Peter Apps reports

Click here to read the full story

Week 18: ‘It was just reckless optimism wasn't it?’

As the inquiry began cross-examining witnesses for the second module of its phase two work, the picture surrounding just how Grenfell Tower ended up wrapped in such dangerous materials became a little clearer. Nathaniel Barker was keeping an eye on proceedings

Click here to read the full story

Week 19: ‘And that was intentional, deliberate, dishonest?’

The Grenfell Tower Inquiry this week heard the shocking story of how the insulation manufacturer “manipulated” official testing and marketed its product “dishonestly”. Peter Apps tells the story

Click here to read the full story

Week 20: ‘We were outed by a consultant who we then had to fabricate a story to’

This week the inquiry investigated the actions of Kingspan – the manufacturer of one of the insulation products used in the tower’s cladding system. Dominic Brady reports

Click here to read the full story

Week 21: ‘It’s there in black and white isn't it? We see a complete absence of any consideration of life safety’

The story of insulation giant Kingspan’s testing and marketing of its combustible insulation for high rises was unpacked in minute detail this week. Peter Apps reports

Click here to read the full story

Week 22: ‘All we do is lie in here’

In the third week of evidence from insulation giant Kingspan, the inquiry continued to uncover shocking details about the firm’s behaviour both before and after the Grenfell Tower fire. Lucie Heath reports

Click here to read the full story

Week 23: ‘That would have come as an earthquake to you at the time, would it not?’

This week the inquiry took its deepest dive yet into the inner workings of the cladding manufacturer whose product has been blamed for the terrible spread of fire up Grenfell Tower. Nathaniel Barker reports

Click here to read the full story

Week 24: ‘Do you accept that Test 5B was Arconic's deadly secret’

The president of the firm that made and sold the cladding panels installed on Grenfell Tower was asked to account for the apparent concealment of “disastrous” fire tests on the product this week. Peter Apps reports

Click here to read the full story

Week 25: ‘This is quite an incredible list of omissions and missed instances, isn’t it?’

This week the Grenfell Tower Inquiry heard its first witnesses from the Building Research Establishment (BRE) - the testing house which carried out key fire tests on the Kingspan and Celotex insulation products which were later used on Grenfell Tower. Peter Apps reports.

Click here to read the full story

Week 26: 'You were taking an enormous risk, weren't you?'

Week 26 at the Grenfell Tower Inquiry was a key moment in understanding how dangerous products used on the tower came to be accepted by industry professionals. Dominic Brady reports

Click here to read the full story

Week 27: ‘What will happen if one building made out [of] PE core is in fire and will kill 60 to 70 persons?’

The most explosive evidence this week at the Grenfell Tower Inquiry came from those who did not attend, as the evidence which would have been presented to Arconic witnesses was displayed in their absence. Peter Apps reports

Click here to read the full story

Week 28: ‘This is a serious safety matter’

This week the Grenfell Tower Inquiry zeroed in on the British Board of Agrément, the body that produced “misleading” certificates which inspired trust in both the cladding and insulation used on the tower. Lucie Heath reports

Click here to read the full story

Week 29:  ‘Is it true that Kingspan’s position… was to do its best to ensure that science was secretly perverted for financial gain?’

The final week in this section of the Grenfell Tower Inquiry primarily examined the attempts by insulation manufacturer Kingspan to lobby government after the fire. Peter Apps reports

Click here to read the full story

How the products used in Grenfell Tower's cladding system were tested and sold

As the section of the Grenfell Tower Inquiry examining how the products used in the cladding system were tested, marketed and sold comes to a close, Peter Apps summarises what we have learned about each of the products included in the system

Click here to read the full story

Module Three: the management of the tower

Week 30: ‘There is certainly a high probability that in the event of a fire the whole building can become an inferno’

The focus of the inquiry shifted this week to the actions of the social housing providers responsible for maintaining Grenfell Tower. Pete Apps recaps what we learned

Click here to read the full story

Week 31: ‘If we cannot get out people will die’

This week saw the former residents of Grenfell Tower enter the witness box to tell of their experiences attempting to raise complaints with the council and its managing agent. Pete Apps reports

Click here to read the full story

Week 32: ‘Let's hope our luck holds and there isn't a fire’

This week saw the return of the landlord of Grenfell Tower, Kensington and Chelsea Tenant Management Organisation (KCTMO), as senior staff members attempted to explain how vital fire safety protections at the block were allowed to fall into disrepair. Lucie Heath reports

Click here to read the full story

Week 33: ‘Isn't that a serious gap in the scope of a policy meant to safeguard vulnerable people?’

A slightly disjointed week at the Grenfell Tower inquiry saw further evidence from staff at building manager Kensington and Chelsea Tenant Management Organisation (KCTMO) interspersed with the views of a cladding expert. Peter Apps reports

Click here to read the full story

Week 34: ‘Some members of the community are doing their best to spread false information’

Jack Simpson covers all the major revelations from the past week of evidence at the Grenfell Inquiry, including evidence from Laura Johnson, director of housing at the Royal Borough of Kensington and Chelsea.

Click here to read the full story  

Week 35: ‘I really didn’t like the champagne’ 

This week the Grenfell Tower Inquiry saw council witnesses, including former deputy leader Rock Feilding-Mellen and leader Nicholas Paget-Brown, questioned about their role in the story for the first time. Peter Apps reports

Click here to read the full story

Week 36: ‘Is that not a very incurious approach for a fire risk assessor?’

This week the Grenfell Tower Inquiry scrutinised the work of Carl Stokes, the man hired to carry out fire risk assessments for the block. Nathaniel Barker reports

Click here to read the full story

Week 37: ‘In giving that advice, weren’t you acting beyond your knowledge and expertise?’

A curtailed week at the Grenfell Tower Inquiry saw fire risk assessor Carl Stokes grilled over advice he gave regarding the tower’s cladding. Peter Apps reports

Click here to read the full story

Week 38: ‘Well it’s a bit more than that, isn’t it. He’s suggesting that you tell the LFB a lie’

The inquiry heard the mammoth cross-examination of KCTMO’s health and safety manager Janice Wray this week. Peter Apps reports

Click here to read the full story

Week 39: ‘What you said there was a grotesque understatement’

This week the inquiry continued to hear from former employees of Kensington and Chelsea Tenant Management Organisation, as well as two employees from the London Fire Brigade. Lucie Heath reports

Click here to read the full story

Week 40: ‘An exercise in concealment and half-truth’

Former KCTMO chief executive Robert Black gave his evidence to the inquiry this week and was asked to account for the various failures described over the previous six weeks. Peter Apps and Nathaniel Barker report.

Click here to read the full story

Week 41: ‘We should do nothing. This is not the sort of website we should be responding to’

This week saw the return of Robert Black, chief executive of Kensington and Chelsea Tenant Management Organisation (KCTMO), before the inquiry turned its attention to the defective smoke control system in the tower. Dominic Brady reports

Click here to read the full story

Week 42:‘They would leak as much as they leaked. They were what they were’

The Grenfell Tower Inquiry continued its in-depth investigation of the tower’s non-compliant smoke control system this week, with evidence from the various contractors involved in delivering it. Pete Apps reports 

Click here to read the full story

Week 43:‘Contractors at the time were not generally aware of the importance of leaving holes unsealed’

This week the inquiry focused on two of the more overlooked areas of the Grenfell Tower fire, with evidence focusing on the gas pipelines and lifts within the west London block. It was a packed week, with five witnesses giving evidence. Jack Simpson reports

Click here to read the full story

Week 44:‘I've never seen a fully compliant firefighting lift in any local authority building, to this day actually’

This week the inquiry turn the focus onto the building’s defective lifts, with evidence from an expert, contractors who worked on them and a former engineer at KCTMO. Pete Apps reports. 

Click here to read the full story

Week 45: ‘Don’t you find all this rather a surprising debate, given that the Equality Act was passed in 2010?’

The inquiry heard from expert witness Colin Todd this week, who gave his views about the work of risk assessor Carl Stokes as well as answered questions about his own guidance. Peter Apps and Nathaniel Barker report

Click here to read the full story

Week 46: ‘I think I've been very, very clear that is completely wrong’

This week the inquiry heard further expert evidence about fire risk assessor Carl Stokes’ actions, as the section of its work covering the management and maintenance of the tower concluded. Peter Apps reports

Click here to read the full story

Six key failures in the way Grenfell Tower was managed before the fire

Peter Apps recaps some of what we have learned about the actions of the Royal Borough of Kensington and Chelsea (RBKC) and Kensington and Chelsea Tenant Management Organisation (KCTMO) in the years before the fire.

Module one and two closing statements

Week 47: ‘An unedifying spectacle’

After a week of closing statements from the core participants involved in modules one and two, Lucie Heath recaps the key arguments of each group

Click here to read the full story

Module five: the fire brigade

Week 48: ‘They knew, and lives could and should have been saved’

The phase of the Grenfell Tower Inquiry examining the actions of the London Fire Brigade in the years before the fire kicked off this week with some major revelations. Peter Apps reports

Click here to read the full story

Week 49: ‘I'm not sure we've always taken every opportunity to learn as an organisation’

How the London Fire Brigade acted upon lessons from incidents in the years before the Grenfell Tower disaster came under the microscope this week at the public inquiry. Nathaniel Barker reports

Click here to read the full story

Week 50: ‘There is a culture in LFB that is very conservative. I think there is great comfort in what is familiar’

This week the inquiry heard how the London Fire Brigade (LFB) elected not to issue warnings about dangerous cladding before Grenfell and a detailed examination of its policy for checking high risk buildings. Pete Apps reports. 

Click here to read the full story

Week 51:‘We teach firefighters to expect building failure’

An unusually brief week of evidence at the Grenfell Tower Inquiry explored how a fire service neighbouring London was taking a different approach to tackling blazes in high rises. Nathaniel Barker reports

Click here to read the full story

Week 52: ‘I actually think that there is a measure of incompetence at all levels’

Expert evidence concluded the current section of the inquiry with some stinging criticism of the London Fire Brigade (LFB). Pete Apps and Grainne Cuffe report. 

Click here to read the full story

Module six: fire services

Week 53: ‘They make for chilling reading and harrowing listening’

The inquiry’s investigation into central government began this week with lawyers setting out their view on how and why firefighting policies failed. Peter Apps and Lucie Heath report

Click here to read the full story

Week 54: ‘Our consideration of evacuation at this time was something of a blind spot’

The development of policy on ‘stay put’, both nationally and for London, occupied the attention of the inquiry this week. Peter Apps reports

Click here to read the full story

Week 55: ‘My review is pretty scathing!’

In a week that included the 200th day of evidence in phase two of the inquiry, attention turned to the London Fire Brigade’s control room. Lucie Heath reports

Click here to read the full story

Week 56: ‘Why didn't we thump the table harder’

This week, the control room at the London Fire Brigade was examined further – both before and after the fire. Pete Apps and Lucie Heath report

Click here to read the full story

Week 57: ‘It was worse than slow, it was sluggish’

Former London Fire Brigade (LFB) commissioner Dany Cotton was the star witness this week, as the inquiry continued to delve into the brigade’s knowledge and training before the Grenfell Tower fire. Jack Simpson, Grainne Cuffe and Pete Apps report

Click here to read the full story

Week 58: ‘I don't think we deserve to ask for trust until we demonstrate different outcomes’

A current and former commissioner of the London Fire Brigade (LFB) wrapped up the inquiry’s investigation into the actions of the brigade before the fire. Grainne Cuffe and Peter Apps report.

Module six: testing and government 

One of the major scandals of our time: key revelations as the Grenfell Tower Inquiry turns to government

The government was accused of “covering up” the risks of dangerous cladding as its “unbridled passion for deregulation” left it a “junior party” to the construction industry as the latest phase of the public inquiry opened today. Peter Apps summarises some of the main points

Click here to read the full story

Week 59: ‘Recent tests have apparently shown it continued to burn for 20 minutes after the flame was taken away’

After shocking opening statements, the Grenfell Tower Inquiry turned its attention to the work of Local Authority Building Control. Pete Apps reports

Click here to read the full story

Week 60: ‘You could have an exact repeat of the Dubai fire in any number of buildings in London’

The Grenfell Tower Inquiry turned its attention to the work of the National House Building Council this week, with shocking revelations about the extent of the warnings issued to central government before the fire. Peter Apps reports

Click here to read the full story

Week 61: ‘Mistakes are meant for learning, not repeating’

In the first hearings of the new year, the Grenfell Tower Inquiry heard closing statements from the firefighting section of phase two. Lucie Heath reports

Click here to read the full story

Week 62: Did it ever occur to you that this act of collaboration was, in one sense, corrupting?

The Grenfell Tower Inquiry returned to the work of the National House Building Council (NHBC) this week, with a new shocking revelation about the government’s actions in the immediate aftermath of the fire. Peter Apps reports

Click here to read the full story

Week 63: ‘It came after the general move to deregulation. So more regulation was not welcome’

The government’s focus on deregulation before the Grenfell Tower fire was placed in the spotlight this week with a series of shocking revelations about its failure to amend fire safety guidance. Pete Apps and Grainne Cuffe report

Click here to read the full story

Week 64: ‘I didn’t think ACM would be suitable for use in any high-rise buildings. I don’t think anyone did’

This week, the Building Research Establishment’s Dr Sarah Colwell gave more than three days of evidence, with some huge revelations about what was known about the dangers of aluminium composite material years before the fire and the mass confusion over the government’s building regulations. Peter Apps and Jack Simpson report

Click here to read the full story

Week 65: ‘Unless the government does something now about ACM panels, people will die’

Further evidence from the Building Research Establishment and the first government witnesses added new depth to our understanding of how warnings were missed before the Grenfell Tower fire. Peter Apps reports 

Click here to read the full story

Week 66: ‘Was there a cover-up?’

The latest evidence from the Grenfell Tower Inquiry tracked the government’s failure to act on fire safety warnings right up until the months before the fire. Peter Apps and Grainne Cuffe report

Click here to read the full story

Week 67: ‘When exposed to a fire, the aluminium melts away and exposes the polyethylene. Whoosh!’

This week the inquiry heard disturbing new evidence about the failure of senior government officials to act on warnings about dangerous cladding in the years before the Grenfell Tower fire. Peter Apps reports

Click here to read the full story

Week 68: ‘Can we agree that was a pretty dangerous thing to have, all this falling on one man’s shoulders?’

Three senior civil servants gave evidence this week, including the official who had responsibility for building regulations guidance on fire safety in the years before Grenfell. Peter Apps, Lucie Heath, Stephen Delahunty and Grainne Cuffe report

Click here to read the full story

Week 69: ‘It was just unthinkable. You had the makings here of a crisis you could not comprehend’

This week, civil servant Brian Martin gave his long-awaited evidence to the Grenfell Tower Inquiry. Peter Apps reports

Click here to read the full story

Week 70: ‘Show me the bodies’

An important week at the Grenfell Tower Inquiry saw a dramatic conclusion to the mammoth cross-examination of civil servant Brian Martin, as well as the first politicians. Peter Apps and Lucie Heath report

Click here to read the full story

Week 71: ‘I have changed my schedule to fit this in. I do have an extremely busy day meeting people’

Three politicians who were responsible for building regulations before Grenfell appeared before the inquiry this week, including the former communities secretary Eric Pickles, who responded to the coroner’s letter following the Lakanal House fire. Peter Apps and Lucie Heath report

Click here to read the full story

Module Four: aftermath

Week 72: 'The system isn't broken. It was built this way'

This week the inquiry turned to the shocking story of the lack of support for bereaved and survivors in the immediate aftermath of the Grenfell Tower fire. Peter Apps, Lucie Heath, Grainne Cuffe and Jack Simpson report

Click here to read the full story

Week 73: ‘Most people would regard that as hopeless’

This week, the Grenfell Tower Inquiry heard about the Royal Borough of Kensington and Chelsea’s chaotic response in the immediate aftermath of the blaze, from the staff responsible for it. Pete AppsStephen Delahunty and Grainne Cuffe report

Click here to read the full story

Week 74: ‘Do you agree that RBKC was ill-prepared and incapable to meet its duties’

This week, Nicholas Holgate, former chief executive of the Royal Borough of Kensington and Chelsea, was grilled on his failure to hand over control of the aftermath of the fire, despite the borough’s lack of capacity. Peter Apps reports

Click here to read the full story

Week 75: ‘It still shocks me to the core that that’s how we treat our citizens in this country’

This week the inquiry heard witnesses from the housing management body discuss their role in the aftermath of the Grenfell Tower fire, followed by a range of witnesses from other organisations which supported the response. Peter Apps and Grainne Cuffe report

Click here to read the full story

Week 76: ‘I fear this will become our New Orleans’

This week the inquiry heard from central government figures and members of the London-wide emergency response arrangements. Peter Apps and Grainne Cuffe report

Click here to read the full story

Week 77: ‘The planning wasn’t done and there was nothing for us to be drawing on’

The Grenfell Tower Inquiry’s examination of the aftermath of the fire concluded with witnesses from central government. Peter Apps reports

Click here to read the full story

Module seven: expert evidence and closing statements

Week 78: ‘The abandonment of the ‘stay put’ strategy for high-rise residential buildings is essential’

This week the Grenfell Tower Inquiry heard a range of expert witnesses discuss their reports. Peter Apps and Grainne Cuffe report

Click here to read the full story

Week 79: ‘You could argue the system was created to enable people to circumvent the rules’

The Grenfell Tower Inquiry continued to hear expert evidence this week, with two senior figures in the world of fire safety academia criticising the government’s approach before and after the blaze. Peter Apps and Grainne Cuffe report 

Click here to read the full story

Week 80: ‘The evidence points to wilful blindness and complacency towards safety’

As the inquiry moves into its final stages, lawyers for the key players gave statements about the evidence surrounding central government. Peter Apps reports

Click here to read the full story

Week 81: ‘This is Islamophobia. It’s racism. It is the elephant staring back at us in the room’

This week, closing statements covering the aftermath of the fire delivered a shocking new revelation and an expert toxicologist gave his views on the causes of the deaths. Peter Apps reports

Click here to read the full story

Module eight: further evidence relating to the deceased

Week 82: ‘Their chance to hear about the circumstances in which their loved ones died is the culmination of five years of waiting’

The Grenfell Tower Inquiry moved into its final module this week, with evidence relating to the circumstances in which the victims died. Peter Apps reports

Click here to read the full story

Week 83: ‘They died together as they lived: caring for one another’

A second week of evidence relating to the circumstances in which the victims of the fire died delivered more heartbreaking stories about their final moments. Peter Apps recaps

Click here to read the full story

Week 84: ‘Every decision affects someone who is an adored child, a beloved sister, a respected uncle, a needed mother’

The final week of oral evidence for the Grenfell Tower Inquiry’s second phase contained more heartbreaking evidence about the deaths in the tower. Peter Apps reports

Click here to read the full story

Closing statements

Week 85: ‘The merry-go-round turns still, the notes of its melody clearly audible in the last few days’

The Grenfell Tower Inquiry returned this week for closing statements from lawyers representing the bereaved and survivors and the various parties under scrutiny for the fire. Pete Apps reports.  

Click here to read the full story

Sign up for our weekly Grenfell Inquiry newsletter

Sign up for our weekly Grenfell Inquiry newsletter

Each week we send out a newsletter rounding up the key news from the Grenfell Inquiry, along with the headlines from the week

New to Inside Housing? Click here to register and receive the weekly newsletter straight to your inbox

Already have an account? Click here to manage your newsletters

Linked InTwitterFacebookeCard
Add New Comment
You must be logged in to comment.
RELATED STORIES
By continuing to browse this site you are agreeing to the use of cookies. Browsing is anonymised until you sign up. Click for more info.
Cookie Settings